ACE Weekly Report 09-19-01

All ACE spacecraft subsystems are performing nominally.
An attitude maneuver was performed on 09/14/01.  The next
attitude maneuvers are scheduled for 09/20/01 and 9/26/01.

The FOT has completed its checkout of the relocated string 3
in Building 14, W10F.  String 2 is scheduled to be moved next
week; the move date is TBD.

Anomalies:
G01-0094:  9/17/2001 ACE experienced ~4 minute delay in
command capability.  The FOT notified the Station, who fixed
the problem shortly thereafter.  No further problems were
experienced during the support (DR#M100160).