ACE Weekly 07/22/05 - 07/28/05

All ACE spacecraft subsystems are performing nominally.

============================================================================
Orbit/Attitude:

	Type         Attitude
	Date         07/22/05
	DOY          203 2005
	Thrusters    2R 4R+ 4R-
	Duration     11:23 min
	Start Time   15:23:25z
	Stop Time    15:34:48z
	Firing       58 pulses

The next attitude maneuver is scheduled for Monday 08/01/05.

============================================================================
OCRs:

None

============================================================================
Ongoing Activities:

Space Link Extension (SLE) - Development continues within the TDF
configuration.  The DSN/Developer test with DTF-21 has been cancelled due to
inability to transition to the Restricted IONet until the Shuttle returns.
The next test is scheduled for 08/25/05.

ROBOTT - FOT testing of Version 1.0 has been completed on String 3.  Version
1.0 was installed on String 2 on Thursday 07/28/05.  Testing of the
installation is underway.  String 1 has been configured for single string
failover.

============================================================================
Extra Activities:

DOY 207 (07/26/05) Active C&DH Block Bins 0-127 downloaded and verified.

============================================================================
Anomalies:

None