ACE Weekly 11/17/05 - 11/23/05

All ACE spacecraft subsystems are performing nominally.

============================================================================
Orbit/Attitude:

	Type         Attitude
	Date         11/22/05
	DOY          236 2005
	Thrusters    2R 4R+ 4R-
	Duration     6:48 min
	Start Time   19:28:18z
	Stop Time    19:35:06z
	Start HGA    4.18 deg
	Stop HGA     6.38 deg
	Firing       35 pulses

The next attitude maneuver is scheduled for Friday 12/02/05.

============================================================================
OCRs:

None

============================================================================
Ongoing Activities:

Space Link Extension (SLE) - ACE SLE development has been become a top
priority.  The next software test including the long duration test with
DTF-21 is scheduled for November 30.  The first delivery is expected in
December with FOT testing beginning in January.  

RIONet - String 3 is anticipated to move to the RIONet within a month.

============================================================================
Extra Activities:

None

============================================================================
Anomalies:

DOY 322 (11/18/05)  G05-0143  TAPS Unable to Save Presets
The ac1taps1 machine is unable to save pre-sets for plots, tables or
reports.  ac2taps2 does not have this problem.
IMPACT: Pre-sets will need to be created on ac2taps2 and copied over to
ac1taps1 until the problem is resolved.