ACE Weekly 03/10/06 - 03/16/06

All ACE spacecraft subsystems are performing nominally.

============================================================================
Orbit/Attitude:

	Type         Attitude     Attitude
	Date         03/10/06     03/10/06
	DOY          069 2006     069 2006
	Thrusters    2R 4R+ 4R-   2R 4R+ 4R-
	Duration     6:40 min     6:54 min
	Start Time   15:33:48z    17:00:24z
	Stop Time    15:40:28z    17:07:18z
	Start HGA     4.77 deg     5.70 deg
	Stop HGA      5.70 deg     6.48 deg
	Firing       34 pulses    36 pulses

The next attitude maneuver is scheduled for Wednesday 03/22/06.

============================================================================
OCRs:

None

============================================================================
Ongoing Activities:

Space Link Extension (SLE) - The first version of ACE SLE was delivered to
the Library on December 14.  The delivery to the ACE MOC will not be until
after String 3 is converted to the RIONET.  

RIONet - String 3 conversion to the RIONet is on hold based on NASCOM's
schedule.    

Attitude Training - The FOT continues training on attitude determination,
maneuver planning, and maneuver execution.

============================================================================
Extra Activities:

None

============================================================================
Anomalies:

None