ACE Weekly 03/24/06 - 03/30/06

All ACE spacecraft subsystems are performing nominally.

============================================================================
Orbit/Attitude:

No attitude maneuvers were completed this week.  The next attitude and
station-keeping maneuvers are scheduled for Wednesday 04/05/06.

============================================================================
OCRs:

None

============================================================================
Ongoing Activities:

Space Link Extension (SLE) - The first version of ACE SLE was delivered to
the Library on December 14.  The delivery to the ACE MOC will not be until
after String 3 is converted to the RIONET.  

RIONet - String 3 conversion to the RIONet is on hold based on NASCOM's
schedule.    

Attitude Training - The FOT continues training on attitude determination,
maneuver planning, and maneuver execution.

============================================================================
Extra Activities:

DOY 083 (03/24/06) - Quartly security scans were performed.  No
vulnerabilities were found.

============================================================================
Anomalies:

DOY 089 (03/30/06)  G06-0026  ROBOTT/C&C Froze
ROBOTT froze after procedure S_OPS_PLBK_COMPLETE completed (EOT-5minutes).
RTMON restart not performed since 5 minutes before End of Track.
CDSID#00021192
IMPACT:  Procedure G_ACEDOWN not executed, status reports not completed
before TPOCC terminated.