ACE Weekly 08/25/06 - 08/31/06

All ACE spacecraft subsystems are performing nominally.

============================================================================
Orbit/Attitude:

	Type        Attitude       
	Date        08/30/2006     
	DOY         242 2006       
	Thrusters   2R 4R- 4R+     
	Duration    8:19 min       
	Start       15:26:30z      
	Stop        15:34:49z      
	StartHGA    5.40 deg               
	StopHGA     6.34 deg               
	Firing      42 pulses      
	FinalSCMass 1395.266lbs    

The next attitude maneuver is scheduled for Thursday, 09/07/06.

============================================================================
OCRs:

None

============================================================================
Ongoing Activities:

Attitude Training - The FOT continues training on attitude determination,
maneuver planning, and maneuver execution.  The transition date is
tentatively scheduled for 08/18/06.

RIONET - The transition to the RIONET on String 3 will tentatively occur
around mid-September.  

Space Link Extension (SLE) - ACE SLE version 2.1 was delivered to the
Library on April 28, 2006.  The delivery to the ACE MOC will not occur until
after the MOC is converted to the RIONET.

Multi-Mission MOC - The FOT has begun supporting the effort to determine the
feasibility of transferring to a multi-mission MOC.

Automation - Development for the next ROBOTT automation release in ongoing
on String 3.  A ROBOTT SPS release is expected no later than September 18.

============================================================================
Extra Activities:

None

============================================================================
Anomalies:

None