ACE Weekly 11/17/2006 - 11/23/2006

All ACE spacecraft subsystems are performing nominally.

============================================================================
Orbit/Attitude:

	Type        Attitude
	Date        11/17/2006
	DOY         321 2006
	Thrusters   2R 4R- 4R+
	Duration    7:51 min
	Start       20:18:02z
	Stop        20:25:53z
	StartHGA    -5.53 deg
	StopHGA     +5.62 deg
	Firing      40 pulses
	FinalSCMass 1394.526lbs

The next attitude maneuver is scheduled for Monday, 11/27/2006.

============================================================================
OCRs:

DOY 325 (11/21/2006)  GND-171
The ground clock calibration epoch was reset to the original value
calculated after launch which is 1997 237 15:48:24.604.  This epoch will be
used starting with the clock calibration report for DOY 324 2006.

DOY 325 (11/21/2006)  GND-175
The ROBOTT SPS patch to provide the SPS password in the SOAP request was
installed on ACEDDS.  On 10/25/2006, DSN upgraded to SPS V1.0.5b which
requires this password.  Testing is underway.

DOY 326 (11/22/2006)  GND-174
TPOCC r5.3 was installed on String 2.  Testing of the installation is
underway.


============================================================================
Activities:

Automation - DSN has postponed the transition to SPS until January 2007
(originally set for 11/27/2006).  This will provide enough time for testing
and a smooth transition for operations.

RIONET - String 3 IP addresses will be configured for the RIONet 11/28/2006
through 11/30/2006 (DOY 332-334).  The next RIONet meeting is scheduled for
11/28/2006.

Space Link Extension (SLE) - ACE SLE version 2.1 was delivered to the
Library on April 28, 2006.  Installation in the ACE MOC will not occur until
after the MOC is converted to the RIONET.

============================================================================
Anomalies:

None