All ACE spacecraft subsystems are performing nominally.

============================================================================
Orbit/Attitude:

	Type        Attitude
	Date        07/02/2007
	DOY         183 2007
	Thrusters   2R 4R+ 4R-
	Duration    12:57 min
	Start       13:54:10z
	Stop        14:07:07z
	StartHGA    -5.40
	StopHGA     +7.29
	Firing      66 pulses
	FuelUsed    0.2174lbs
	FuelRemain  155.9988lbs
	FinalSCMass 1390.259lbs

The next attitude maneuver is scheduled for Friday, 07/13/2007.

============================================================================
OCRs:

None

============================================================================
Activities:

RIONET - Testing and configuration continue for String 1 on the Restricted
IONet.  DSN monitor data is not yet being delivered.

ROBOTT - ROBOTT v1.0.3 upgrade will be installed on String 1 on Monday
07/09/2007.  This upgrade is needed for ROBOTT to work on the Restricted
IONet.

Space Link Extension (SLE) - ACE SLE version 2.1 was delivered to the
Library on April 28, 2006.  Installation in the ACE MOC will not occur until
after the MOC is converted to the RIONET.

DSN/SPS/FDF - FDF is now delivering a 12 week predictive ephemeris which
will satisfy the DSN SPS requirements.  However, the original problem (ACE
viewperiod files starting in the future) was fixed when SPS corrected their
own timer configuration.

Planning continues for integrating ACE operations into a multi-mission ops
center (MMOC).

============================================================================
Anomalies:

None

Update on AR#G07-0055 - Problems with String 2 were fixed by replacing the
front end workstation motherboard.  Replacement parts, however, are becoming