ACE Weekly 06/29/2007 - 07/05/2007 All ACE spacecraft subsystems are performing nominally. ============================================================================ Orbit/Attitude: Type Attitude Date 07/02/2007 DOY 183 2007 Thrusters 2R 4R+ 4R- Duration 12:57 min Start 13:54:10z Stop 14:07:07z StartHGA -5.40 StopHGA +7.29 Firing 66 pulses FuelUsed 0.2174lbs FuelRemain 155.9988lbs FinalSCMass 1390.259lbs The next attitude maneuver is scheduled for Friday, 07/13/2007. ============================================================================ OCRs: None ============================================================================ Activities: RIONET - Testing and configuration continue for String 1 on the Restricted IONet. DSN monitor data is not yet being delivered. ROBOTT - ROBOTT v1.0.3 upgrade will be installed on String 1 on Monday 07/09/2007. This upgrade is needed for ROBOTT to work on the Restricted IONet. Space Link Extension (SLE) - ACE SLE version 2.1 was delivered to the Library on April 28, 2006. Installation in the ACE MOC will not occur until after the MOC is converted to the RIONET. DSN/SPS/FDF - FDF is now delivering a 12 week predictive ephemeris which will satisfy the DSN SPS requirements. However, the original problem (ACE viewperiod files starting in the future) was fixed when SPS corrected their own timer configuration. Planning continues for integrating ACE operations into a multi-mission ops center (MMOC). ============================================================================ Anomalies: None Update on AR#G07-0055 - Problems with String 2 were fixed by replacing the front end workstation motherboard. Replacement parts, however, are becoming scarce.