ACE Weekly 06/29/2010 - 07/06/2010 All ACE spacecraft subsystems are performing nominally. ======================================================================== Orbit/Attitude: Type Attitude Date 07/01/2010 DOY 182 2010 Thrusters 2R 4R+ 4R- Duration 10:38 min Start 14:43:22z Stop 14:54:00z HGAStart -3.01deg HGAStop +7.77deg SunStart 8.76deg SunStop 17.20deg SpinStart 5.0586rpm SpinStop 5.0609rpm Nutation 0.11deg Firing 54 pulses FuelUsed 0.1748lbs FuelRemain 135.2368lbs FinalSCMass 1369.497lbs The next attitude maneuver is scheduled for Thursday 07/15/2010. ======================================================================= OCRs: None ======================================================================== Activities: Data Capture: 100% DOY 178-185 2010 ======================================================================== Anomalies: None