ACE Weekly 06/29/2010 - 07/06/2010

All ACE spacecraft subsystems are performing nominally.

========================================================================
Orbit/Attitude:

	Type        Attitude
	Date        07/01/2010
	DOY         182 2010
	Thrusters   2R 4R+ 4R-
	Duration    10:38 min
	Start       14:43:22z
	Stop        14:54:00z
	HGAStart    -3.01deg
	HGAStop     +7.77deg
	SunStart     8.76deg
	SunStop     17.20deg
	SpinStart   5.0586rpm
	SpinStop    5.0609rpm
	Nutation     0.11deg
	Firing      54 pulses
	FuelUsed      0.1748lbs
	FuelRemain  135.2368lbs
	FinalSCMass 1369.497lbs

The next attitude maneuver is scheduled for Thursday 07/15/2010.

=======================================================================
OCRs:

None

========================================================================
Activities:

Data Capture:  100%  DOY 178-185 2010


========================================================================
Anomalies:

None