ACE Weekly 08/09/2011 - 08/16/2011 All ACE spacecraft subsystems are performing nominally. ======================================================================== Orbit/Attitude: Type Attitude Date 08/10/2011 DOY 222 2011 Thrusters 2R 4R+ 4R- Duration 5:11 min Start 14:25:49z Stop 14:31:00z HGAStart +3.40deg HGAStop +7.84deg SunStart 4.84deg SunStop 9.68deg SpinStart 5.0103rpm SpinStop 5.0115rpm Nutation 0.17deg Firing 26 pulses FuelUsed 0.0907lbs FuelRemain 127.2836lbs FinalSCMass 1361.544lbs The next attitude maneuver is scheduled for Tuesday 08/30/2011. ======================================================================= OCRs: None ======================================================================== Activities: Data Capture: 100% DOY 219-226 2011 The GRAIL mission is expected to launch 09/08/2011. ACE has reduced DSN antenna time during September. The current schedule has ACE losing ~15% data over 3 weeks in September. The data loss will be greater if there are problems with any of the passes. SOLAR EXCLUSION ZONE (SEZ): On Wednesday (8/17/2011), ACE will get to 0.78 degrees from the center of the sun (as seen from Earth) and will get closer in the upcoming transits. DSN is not expected to have any problems receiving high-rate data (87648bps) when the Sun-Earth-Vehicle (SEV) angle is greater than 0.5 degrees. The SSR recorders are large enough (2x43 hours) to record all science data while the SEV angle is less than 0.5 degrees. 08/17/2011 0.78 degrees 11/14/2011 0.41 degrees 02/08/2012 0.18 degrees 05/06/2012 0.71 degrees 08/05/2012 1.23 degrees NOAA Space Weather Prediction Center (SWPC) server is again having problems processing the high-rate real-time data (1 frame per second) from the MMOC on Sunday 08/14/2011 and Monday 08/15/2011. This last occurred on 07/26/2011 and 07/27/2011. ======================================================================== Anomalies: DOY 222 08/10/2011 S-ACE-0623 G11-0050 MUS CMD process terminated The MMOC SLE (MUS) cmd process (ace-d27-cmd) terminated unexpectedly 2 minutes after beginning of track. The MUS CMD process was restarted and the process died a second time. MUS CMD was restarted and no further problems occurred. This last occurred for ACE on 03/22/2010 (AR#G11-0023) IMPACT: Manual intervention required. DOY 223 03/11/2011 S-ACE-0624 G11-0051 MUS CMD unable to BIND The MMOC SLE (MUS) cmd process (ace-d27-cmd) generated the error "Cannot send a BIND because of the following Anite error condition: ace-d27-cmd's F-CLTU provider object could not thread off an Operations server because". This error has not occurred before. MUS CMD was restarted and no further problems occurred. IMPACT: Manual intervention required. DOY 225 03/13/2011 S-ACE-0624 G11-0051 MUS CMD unable to BIND The same problem as DOY 223 occurred. The MMOC SLE (MUS) cmd process (ace-d27-cmd) generated the error "Cannot send a BIND because of the following Anite error condition: ace-d27-cmd's F-CLTU provider object could not thread off an Operations server because". This error has not occurred before. MUS CMD was restarted and no further problems occurred. (DR# 111882) IMPACT: Manual intervention required. Activities delayed 20 minutes. There were no MUS CMD problems on Sunday DOY 226 or Monday DOY 227.