ACE Weekly 06/18/2014 - 06/24/2014

All ACE spacecraft subsystems are performing as expected.

========================================================================
Orbit/Attitude:

	Type          Attitude
	Date          06/24/2014
	DOY           175 2014
	Thrusters     2R 4R+ 4R-
	Duration       5:33 min
	Start         13:17:39z
	Stop          13:23:12z
	ra,decStart   95.29,39.79
	ra,decStop   101.96,39.24
	ra,decExpect 102.16,39.13
	Deviation      0.19 deg
	HGAStart     -10.93 deg
	HGAStop      +11.04 deg
	SunStart      16.57 deg
	SunStop       17.63 deg
	SpinStart    4.9977 rpm
	SpinStop     4.9991 rpm
	Nutation       0.19 deg
	Firing        18 pulses
	FuelUsed        0.0931 lbm
	FuelRemain    106.1300 lbm
	FinalSCMass   1341.390 lbm

The next attitude maneuver and Station Keeping maneuver #70 are
scheduled for 07/1/2014.

========================================================================
OCRs:

None

========================================================================
Activities:

Data Capture:  100%  DOY 166-173 2014

DSN time is limited for a couple of days in the coming week.  If there
are DSN problems, then data loss (1-10 hours) may occur.  The DSN
schedule is changing, so opportunities to acquire more time may be
possible.

DSN has upgraded the SLE software (v33.4 to v34.1) on their telemetry
servers.  (Space Link Extension is the protocol for data between the
MMOC and DSN.)  DSN transitioned ACE from the SLE4 server (old software)
to SLE3 server (new software) on Tuesday 06/24/2014.  No problems have
been found.  Note, DSN is continually improving and upgrading software;
changes are included in this weekly report only when problems occur or
the FOT is notified of the changes.

========================================================================
Anomalies:

None